Activity-based costing

Also called:ABC

Plain-English definition

Activity-based costing is a costing method that assigns indirect overhead costs to products or services based on the specific activities and cost drivers they actually consume.

Subject CourseManagement AccountingSubject GuideElena Morales
Connected Resources3 lessons · 1 tools & labs
Formula · Activity-based costing

Activity rate = Activity cost pool ÷ Total cost driver volume

Activity cost pool
total indirect cost grouped around a single activity such as machine setups, inspections or order processing
Total cost driver volume
total number of times the activity occurs across all products (for example, total setups or inspections)
Vocabulary: 0/62 (0%)
Progress is saved locally in your browser.

Explanation

Traditional absorption costing usually spreads all factory overheads across products using a single volume measure such as direct labour hours or machine hours. That works well when a business makes one simple product, but it breaks down when a company runs a mix of high-volume standard items and complex small-batch custom orders.

Activity-based costing (ABC) fixes that distortion in three steps: identify the key overhead activities (machine setups, quality checks, purchase orders, customer support), group each activity’s costs into a cost pool with a matching cost driver, and charge each product according to how much of each driver it consumes.

Example

A machine shop incurs $60,000 per quarter in machine-setup overheads and performs 120 setups, giving an activity rate of $60,000 ÷ 120 = $500 per setup. It produces two parts that each use 1,000 machine hours (2,000 hours total):

  • Part A (high-volume standard part): 1,000 machine hours, 20 setups
  • Part B (custom small-batch part): 1,000 machine hours, 100 setups

Under traditional allocation by machine hours ($60,000 ÷ 2,000 = $30/hour), both parts are charged $30,000. Under ABC:

  • Part A setup cost = 20 × $500 = $10,000
  • Part B setup cost = 100 × $500 = $50,000

Traditional costing had overcosted Part A by $20,000 and undercosted Part B by $20,000.

Why it matters

ABC reveals which products, customers or order sizes are genuinely profitable once support complexity is priced in. Companies frequently discover that low-volume “custom” jobs erode gross profit while high-volume bread-and-butter items are subsidising them.

Common confusion

ABC is not a replacement for IFRS or US GAAP external inventory rules, and it is not always worth the data-collection effort for simple businesses with low overheads. Its real value is internal decision-making: pricing, product mix and process improvement. See how ABC compares with job and process costing in job, process and ABC costing.

Subject GuideManagement Accounting & Corporate Finance

Elena Morales

Bridges internal factory numbers and boardroom valuation models step by step.

  • Costing & Variance Analysis
  • FP&A Forecasting
  • WACC & DCF Valuation

More lessons with Elena

Published:

Educational content only—not accounting, tax, legal or investment advice. See our editorial policy or report an error via our corrections policy.

Search