Variance Analysis & Flexed Budget Lab

Examine a month of production at Alder Workshop, a fictional wooden desk manufacturer that budgeted to sell 1,000 desks for a $15,000 operating profit. Adjust actual sales volume, selling price, timber usage and price, labour hours and wages, and fixed overhead to watch the flexed budget and profit bridge reconcile static budget profit to actual profit down to the exact cent.

Live Interactive Sandbox · Runs 100% locally in your browser

Safe fictional data · Reset any time

Try a factory scenario (Alder Workshop)

Static budget: 1,000 desks @ $120 price, 4 kg timber @ $10/kg, 2 hrs labour @ $20/hr, $25,000 fixed overhead.

Static budget profit

$15,000

Planned for 1,000 desks

Flexed budget profit

$19,000

Re-scaled to 1,100 actual desks

Actual profit

$13,820

Reconciliation diff: $0.00

Total profit variance

-$1,180

Adverse (missed static budget)

Profit bridge waterfall (Static → Flexed → Actual)

Green = Favourable (F) · Rose = Adverse (A)
Alder Workshop profit variance waterfall chartStatic budget profit of $15,000 shifts by Sales Volume variance of +$4,000 to Flexed Budget profit of $19,000, then by six operating variances totalling -$5,180 to Actual profit of $13,820.$0$6k$13k$19k$25k$15kStatic+$4kSales Vol$19kFlexed-$4.4kSales Price+$2.3kMat Price-$2.2kMat Usage-$2.1kLab Rate+$2.2kLab Eff-$1kFixed OH$14kActualProfit bridge componentsProfit (USD)
Static budgetFlexed budgetFavourable (F)Adverse (A)Actual profit

What the profit bridge explains

Alder Workshop budgeted $15,000 on 1,000 desks and earned $13,820 on 1,100 desks (a total variance of -$1,180). Flexing the budget to actual sales volume raises the fair benchmark to $19,000. The biggest positive driver is Sales Volume Contribution Variance (+$4,000 F). The biggest drag on profit is Sales Price Variance (-$4,400 A).

Actual workshop performance

1,100 desks

Static budget: 1,000 desks.

$116/desk

Budget standard: $120/desk.

4.2 kg/desk

Standard: 4.0 kg/desk (4,620 kg total vs 4,400 kg std).

$9.50/kg

Standard: $10.00/kg.

1.9 hrs/desk

Standard: 2.0 hrs/desk (2,090 hrs total vs 2,200 hrs std).

$21.00/hr

Standard: $20.00/hr.

$26,000

Budgeted fixed overhead: $25,000.

Complete profit reconciliation statement

Exact reconciliation: Static Budget + Sales Volume = Flexed Budget; Flexed Budget + Operating Variances = Actual Profit.

Alder Workshop full variance reconciliation from static budget to actual profit
Line itemCalculationAmountF / A
Static Budget Profit1,000 desks × $40 std contribution − $25,000 fixed OH$15,000.00—
Sales Volume Contribution Variance(1,100 − 1,000 units) × $40/unit std contribution+$4,000F
Flexed Budget Profit1,100 desks × $40 std contribution − $25,000 fixed OH$19,000.00—
Sales Price Variance($116.00 − $120.00) × 1,100 units-$4,400A
Material Price Variance($10.00 − $9.50) × 4,620 kg+$2,310F
Material Usage Variance(4,400 − 4,620 kg) × $10.00/kg-$2,200A
Labour Rate Variance($20.00 − $21.00) × 2,090 hrs-$2,090A
Labour Efficiency Variance(2,200 − 2,090 hrs) × $20.00/hr+$2,200F
Fixed Overhead Expenditure Variance$25,000 budget − $26,000 actual-$1,000A
Actual ProfitReconciled exactly (diff $0.00)$13,820.00—

Static vs flexed vs actual income statement

Comparison of static budget, flexed budget and actual income statement
LineStatic budgetFlexed budgetActualFlexed vs Actual
Desks sold (units)1,0001,1001,1000
Sales revenue$120,000.00$132,000.00$127,600.00-$4,400
Direct material$40,000.00$44,000.00$43,890.00+$110
Direct labour$40,000.00$44,000.00$43,890.00+$110
Contribution margin$40,000.00$44,000.00$39,820.00-$4,180
Fixed overhead$25,000.00$25,000.00$26,000.00-$1,000
Operating profit$15,000.00$19,000.00$13,820.00-$5,180

Lab guide & concepts

How to use this lab

  1. Choose one of the four factory scenarios (Discounting for volume, Cheap poor-quality material, Overtime crunch, or On-budget baseline) to see realistic trade-offs across departments.
  2. Read the waterfall profit bridge from left to right: start at Static Budget ($15,000), step through Sales Volume to the Flexed Budget, and then trace all six operating variances to Actual Profit.
  3. Move any actual-performance slider on the right to isolate how price, efficiency and volume affect individual green (Favourable) and rose (Adverse) bars.
  4. Use the reconciliation table and the side-by-side income statement below the chart to verify every formula.

Key concepts and formulas

  • Why Flex the Budget? Comparing actual costs for 1,100 desks against a static budget built for 1,000 desks compares apples with oranges. A flexed budget restates variable revenue and variable costs at standard rates for actual units sold, keeping fixed overhead unchanged. See fixed and variable costs and business budgeting.
  • Sales Volume Contribution Variance: (Actual Units − Budget Units) × Standard Contribution per Unit. At Alder Workshop, standard contribution is $120 − $40 material − $40 labour = $40/desk.
  • Sales Price Variance: (Actual Price − Standard Price) × Actual Units.
  • Material Price & Usage Variances:Price = (Std Price/kg − Actual Price/kg) × Actual kg; Usage = (Std kg for Actual Output − Actual kg) × Std Price/kg.
  • Labour Rate & Efficiency Variances:Rate = (Std Rate/hr − Actual Rate/hr) × Actual Hours; Efficiency = (Std Hours for Actual Output − Actual Hours) × Std Rate/hr.
  • Fixed Overhead Expenditure Variance: Budgeted Fixed Overhead − Actual Fixed Overhead.

What to experiment with

  • See how variances interact across departments: Load Cheap poor-quality material. Purchasing earns a big favourable Material Price variance (+$5,750 F), yet factory scrap (-$6,000 A) and rework labour (-$4,000 A) drag total profit down by $4,250.
  • Test a volume-vs-price trade-off: Load Discounting for volume, then nudge Actual Selling Price from $112 up to $114. At what selling price does selling 1,200 desks actually beat the $15,000 static budget?
  • Verify exact reconciliation: Drag every slider to an extreme value and check the Reconciliation Statement — the sum of all seven variances always equals Actual Profit − Static Budget Profit with $0.00 difference.

Model simplifications and assumptions

  • Alder Workshop is a fictional manufacturing model designed for learning marginal-costing variance analysis.
  • All desks produced in the period are sold (no opening or closing work-in-progress or finished-goods inventory), and materials purchased equal materials used.
  • Fixed overhead is analysed under marginal costing (expenditure variance only, with no fixed overhead volume/capacity absorption variance).
  • Standards remain fixed at 1,000 budgeted desks, $120 price, 4 kg/desk @ $10/kg, 2 hrs/desk @ $20/hr, and $25,000 fixed overhead.

Deepen your margin intuition with the profit margin lesson.